Commissioning
4.4 Commissioning with the BOP-2
Inverter with CU240B-2 and CU240E-2 Control Units
70 Operating Instructions, 01/2011, FW 4.4, A5E02299792B AB
Identifying motor data
If you select the MOT ID (p1900) during basic commissioning, alarm A07991 will be issued
once basic commissioning has been completed. To enable the converter to identify the data
for the connected motor, you must switch on the motor (e.g. via the BOP-2). The converter
switches off the motor after the motor data identification has been completed.
CAUTION
Motor data identification for dangerous loads
Secure dangerous plant and system parts before starting the motor data identification, e.g.
by fencing off the dangerous location or lowering a suspended load to the floor.
4.4.5 Additional settings
The Section Commissioning (Page 55) shows you what still has to be set after the basic
commissioning in order to adapt the inverter to your application.