8
Testing XMU
+
Installation
The final step in XMU+ installation is to ensure that the XMU+ is properly
connected to the PBX.
There are two tests that must be completed to confirm that the XMU+
system has been installed correctly:
Test system power and basic processor card operation.
See Testing Basic XMU+ System Health on page 96.
Test the telephone lines connected to the XMU+ to ensure that they are
connected and active. See Testing XMU+ Line Connections on page 100.
In this chapter...
About XMU+ Testing on page 95.
Testing Basic XMU+ System Health on page 96.
Test ing XMU+ Line Connections on page 100.